Reports from the site
Material available for download - For uses of these documents other than single-copy reproduction for own personal use, written permission must be obtained from Scandinavian Biogas Fuels AB (please use contact form available on the website)
- 211115 Site visit n.12 »
- 210507 Site visit n.11 »
- 200223 Site visit n.10 »
- 191126 Report from the site n.7 - Status on operation
- 190923 Site visit n.9 »
- 190226 Site visit n.8 »
- 190107 Site visit n.7 »
- 180906 EU Project visit »
- 180902 Opening Ceremony »
- 180715 Report from the site n.6 - Progress of construction work »
- 180605 Site visit n.6 - Pulp, Paper and Biogas »
- 180305 Site visit n.5 - Lab tests and sampling »
- 180131 Site visit n.4 - Final work before start-up »
- 171223 Report from the site n.5 - Progress of construction work »
- 170928 Site visit n.3 - Machineries in place »
- 170703 Report from the site n.4 - Progress of construction work »
- 170511 Site visit n.2 - Main buildings erected »
- 170510 Report from the site n.3 - Ground works ongoing »
- 170124 Site visit n.1 - Ground works ongoing »
- 161216 Report from the site n.2 - Progress of the engineering work »
- 160615 Report from the site n.1 - Progress of the engineering work »